Change Advisory Board (CAB)
Change Advisory Board (CAB)
Purpose
The Change Advisory Board (CAB) is the formal decision-making body for Major and Minor changes to the BoB standard.
Within the BoB Change Management Process, the CAB is responsible for the final consensus decision on Change Requests that require formal approval.
Participation and Eligibility
Participation in the CAB is limited to organisations that:
Have a valid agreement with Samtrafiken, and
Finance the administration and governance of the BoB standard
Only organisations meeting these criteria may appoint representatives and participate in CAB decisions.
Each eligible organisation appoints a BoB Contact Person, who:
Has decision-making authority for their organisation
Coordinates internal review of Change Requests
Participates in CAB meetings or delegates with formal mandate
Samtrafiken participates through:
The Change Manager (process coordination and chairing)
Technical experts when needed
Scope of CAB Authority
The CAB makes decisions on:
Major changes
Minor changes
Patch changes are handled by Samtrafiken as described in the Change Management Process.
From BoB Tech to CAB
The overall Change Flow is described on the parent page.
In summary:
A proposal is discussed and refined in the BoB Tech forum.
The initiator is responsible for drafting and submitting the formal Change Request.
When ready for decision, Samtrafiken initiates the CAB process.
CAB is the formal decision step within the broader governance structure.
CAB Process
1. Initiation
The CAB process formally begins when Samtrafiken sets a date for a CAB meeting.
Once the meeting date is established, the consultation phase is initiated.
2. Consultation Phase
The Change Manager distributes the Change Request documentation only to BoB Contact Persons in organisations eligible to participate in CAB.
The consultation period:
Is normally at least 30 days
Covers technical, organisational, and business impact
Ensures internal anchoring within each eligible stakeholder organisation
If significant feedback requires adjustments, the proposal may be revised before the CAB meeting.
3. CAB Meeting
CAB meetings are held as needed, based on the maturity and urgency of pending Change Requests.
Decision Principles
Decisions are made by consensus
There is no majority voting
All participating organisations must agree
Participants must have formal mandate
Decision Outcomes
A Change Request may result in:
GO – Approved
NO GO – Rejected
Returned for revision – Sent back for further work before re-submission
All decisions are documented.
4. After Decision
If approved, the decision includes:
Confirmed classification (Major or Minor)
Version number
Implementation and, if applicable, sunset timelines
Samtrafiken implements and publishes the approved change according to the Change Management Process.
If returned for revision, the proposal may be further refined by the initiator through BoB Tech and resubmitted through the standard process.
Governance Principles
CAB decisions reflect the governance principles defined in the BoB Change Management Process:
Formal governance
Transparency
Impact awareness
Consensus-based control
The CAB ensures coordinated evolution of the BoB standard among organisations that jointly finance and govern it.